Tis the season for retrospectives! We’re not going to talk about the whole year though, just our progress for the last quarter, as guided by the first round of the Project Prioritization Process. As you can see below, we’ve accomplished quite a bit, but still have some work to do and will require further resources in future quarters.

Project Results (2013-52)
Google Books Not really a project, removed from listing – still doing it though.
Arrange HathiTrust Content & Access Same as above: Not really a project, removed from listing.
Monographs Lending Report Retrieved data sample, examining for suitability, evaluating methods for dispersal
Patron Data Load via OCIO People service Committed to production January 1, expecting some clean-up afterwards
Migrate PastPerfect to AG-44 Progressing, should be wrapped up this quarter
Migrate CyberSource HOP Pages Not started yet.
KB: Authenticated Sign-On Not started yet.
Identifier Hub Some preliminary discussions, have identified a possible migration path
Explore Video/Audio Repository Software We’ve found a likely candidate for exploration in a future sprint
eResource Usage Statistics Have provided a sample of data to the eResource team, they are evaluating.
Engineering Wiki Transfer Project removed from list by requestor.
DSpace REST API Put into production, shared with DSpace community
DRC Migration IT tasks complete, will assist DCS as necessary
Digital Asset Management Preliminary Discussions
Cartoons Redesign:Release 1 Website deployed
Buckeye Sensor Partnering with Facilities and FOD Automation to deploy pilot sensors in THO
Add HathiTrust API to WebPAC Not started yet.
ABBYY FineReader Key Server Progressing, should be wrapped up this quarter
Staff Directory Overhaul Combined several data sources for a first iteration.
SCCM Deployment Progressing nicely
Infrastructure 2013 Many new servers up and running, awaiting software migrations