Updates for March 13

Ryan Langhurst and Wes Boomgaarden provided this update for the Renovation Committee, which provides a great summary about the current status of the of several aspects of the project. Construction: *We are in month 26 of the 27-month project. Continues to be on time. *Construction trailers will all be removed from the site by March […]